EDW timeline

Our EDW deadline is down to around a month.

During the next 4-5 weeks, we’ll need to finish loading FIS data, FIS fixed assets, finish SIS (degrees, transfer) and start into HR.

We’ve completed our first final report, with 2 more on the way.  The team is experiencing a higher stress level than average (partly because I’m over there every day now), but also knowing that June is in 2 days.

The WOU EDW will be a successful project.  We had hoped to complete it earlier and have users in the warehouse to get feedback.  That will still occur, but probably in late June/early July.